8. You expect that a project will bring in $25,000 USD in revenue per year. You estimate it will cost $12,000 up front. You also estimate costs of $200 per month for the first 12 months, which equals $2,400 per year. Using the formula (G-C) ÷ C = ROI, how would you calculate the project’s return on investment (ROI) after the first 12 months?
1 / 1 point
Correct
Related Questions & Answers:
- Fill in the blank: According to a 2017 Project Management Institute study, industries like manufacturing, construction, information technology, publishing, finance, and oil and gas are experiencing _____ with project management jobs. 2. Fill in the blank: According to a 2017 Project Management Institute study, industries like manufacturing, construction, information technology, publishing, ... Read more...
- When budgeting a project, what is the responsibility of a project manager? 2. When budgeting a project, what is the responsibility of a project manager? 1 / 1 point Setting a period of time ... Read more...
- Which answer best describes the Agile project management methodology? 4.Which answer best describes the Agile project management methodology? 1 / 1 point Created in the eighties, the Agile methodology refers to ... Read more...
- As someone interviewing for a project management role, you ask questions about sick days and vacation, flexible work hours, and employees sharing their identity in the workplace. Which part of a company’s culture do these questions help you learn more about? 8. As someone interviewing for a project management role, you ask questions about sick days and vacation, flexible work hours, ... Read more...
- Which of the following are key components of project initiation? Select all that apply. 3. Which of the following are key components of project initiation? Select all that apply. 1 / 1 point Resources ... Read more...
- As project manager, you approve a team member’s request to change the order of their tasks because they think it will be more efficient. However, this change disrupts another team member’s work process: they need to do two additional tasks not related to the project’s goal. What is happening on this project? 2. As project manager, you approve a team member’s request to change the order of their tasks because they think ... Read more...