Project Risks

Project Risks >> Fundamentals of Project Planning and Management

*Please Do Not Click On The Options.

* If You Click Mistakenly Then Please Refresh The Page To Get The Right Answers.

Project Risks

TOTAL POINTS 10
1 point
 
 
1 point
 
 
1 point
 
 

On the x-axis we have the relative magnitude of the ‘impact,’ with higher numbers indicating a more severe outcome. On the y-axis we have the probability that a risk ‘may’ occur, ranging from just above 0% to just below 100%. Using Risk Score as a measure, prioritize risks A through E from MOST risky to LEAST risky.

1 point
 
 

Consider the project detailed in the table above. Assume every task begins as soon as possible, but lasts its MINIMUM duration. What is the duration of this project as a whole?

1 point
 
 

According to the Tornado Chart above, which task has the potential to cause the GREATEST IMPACT on the project’s OVERALL DURATION?

1 point
 
 

 

7. Figure 4: Cumulative Probability Curve for the duration of Project X

According to the cumulative probability curve above, what is the probability that this project will take AT LEAST 25 weeks to complete?

1 point
 
 

According to the cumulative probability curve above, what is the probability that this project will be completed within 55 weeks?

1 point
 
 
1 point
 
 
1 point
 

Leave a Comment